How Much Does It Cost to Build a Data Center? The Short Answer, Then the Budget

THE SHORT ANSWER

Building a data center costs about US$10 million to US$24 million per megawatt of IT load in 2026 for the facility alone, and about US$53 million per megawatt once B200-class GPUs are included. That puts a 5 MW site near US$61M, a 50 MW powered shell near US$564M and a 100 MW AI factory near US$2.35B, or US$5.33B with GPUs.

Secure checkout by Stripe. The AI Build Configurator runs on your own website under your brand; Enterprise is quoted — compare all tiers. Annual licence. All Licence Terms and Terms of Service must be read and agreed. Terms of Service · Licence Terms

Engineers reviewing a data center construction budget, phase by phase, on site

How Much It Costs per Megawatt, by Build Type

The honest answer is "it depends on what you build", so here is the spread for a 50 MW project in Texas, before GPUs, from the SCR AI Build Configurator dataset:

Facility build cost per MW of IT load, Texas, 50 MW, default cooling, before GPUs. SCR AI Build Configurator v1.4.0, data vintage Q4 2026. US dollars.
Build typePer MW50 MW totalBuild + grid
Hybrid mining + AIUS$6.1MUS$305M16 months
Bitcoin miner retrofitUS$10.0MUS$500M20 months
Powered shell (lease the megawatt)US$11.3MUS$564M30 months
Modular / prefabricatedUS$12.2MUS$610M11 months
Neocloud / GPU-as-a-serviceUS$14.3MUS$715M20 months
Edge / micro deploymentUS$20.8MUS$1.04B8 months
Hyperscale AI factoryUS$23.5MUS$1.18B38 months

Then decide who buys the GPUs. B200-class accelerators add about US$30M per MW, which is why a 100 MW AI factory in Georgia models at US$2.35B for the building but US$5.33B with GPUs. For five fully worked projects, see the cost to build a data center, 5 MW to 100 MW.

Build cost per MW, Texas: before GPUs, 50 MW Fastest build types: months for edge and modular

The Budget, Phase by Phase

Shell and core: of a 50 MW powered-shell build in Texas 50 MW powered shell: Texas, direct-to-chip liquid cooling Design, permits, PM: of hard construction cost

Here is where the money goes on a 50 MW powered shell in Texas with direct-to-chip liquid cooling, grouped into the phases you would see on a site budget:

US$563.9M total, US$11.3M per MW. SCR AI Build Configurator v1.4.0. Line items from our construction cost breakdown.
PhaseWhat it coversCostShare
1. Land and sitingLand plus the utility's connection contributionUS$28.3M5%
2. Site development and core buildShell and core: structure, slab, roof, power roomsUS$319.1M57%
3. Mechanical, electrical and coolingM&E fit-out (US$39.3M) and the cooling plant (US$117.4M)US$156.7M28%
4. NetworkFibre, meet-me rooms, carrier diversityUS$13.1M2%
5. Soft costsDesign, permits and project management (9% of hard cost)US$46.6M8%

Phase 2 is the big number on every budget. The cooling plant is the line that moves most with your choice of technology: liquid cooling costs more up front but is required above about 50 kW per rack.

What Moves the Price Up or Down

  • Build type. The single biggest lever before GPUs: US$6.1M to US$23.5M per MW, as in the table above.
  • Location. Construction cost factors run from 0.86× in Arkansas and Mississippi to 1.30× in Hawaii, with California and New York at 1.22×. The same building can cost 51% more in the most expensive state than in the cheapest.
  • Power price. It doesn't change the build cost, but it decides whether the site pays back: industrial rates in our dataset run from US$0.071/kWh in Texas to US$0.38/kWh in Hawaii. Compare them on the data center cost per MW by state page.
  • Cooling and density. Air, rear-door, direct-to-chip or immersion; denser AI racks need liquid and a bigger cooling plant.
  • GPUs. Optional for the building, but the largest cost of all when you buy them: 56% of a 100 MW AI factory.
Cheapest states to build: Arkansas and Mississippi construction factor Most expensive states: Hawaii; California and New York 1.22×

Hidden Costs People Miss

Build plus grid time: months, edge to hyperscale AI factory Longest waits: Virginia, California and Hawaii

The quote for the building is not the whole bill. These are the costs that catch first-time developers:

  1. Waiting for power. Grid queues run from 26 months in Arkansas to 54 months in New York. Land, interest and staff cost money the whole time.
  2. Large-load tariffs. Some utilities make big users pay for a minimum share of their contracted demand whether they use it or not: 80% for 100 MW+ in Georgia, 85% for 25 MW+ in Virginia and Ohio.
  3. Sales tax on equipment. Most data center states offer an exemption; California (8.85%), New York and Hawaii don't, which adds millions to the fit-out.
  4. The utility contribution. US$17.7M on the 50 MW Texas example, often left out of early estimates.
  5. Soft costs. Design, permits and project management add about 9% to hard construction cost.

Our data center TCO calculator adds the operating side: energy, staffing and payback.

Get a Number for Your Own Site

Every number on this page comes from one dataset, and you can run it for your own site. Pick a US state or Canadian province, build type, size, cooling and GPU class in the free live demo of the AI Build Configurator, and it shows the capital cost line by line, power cost, build time and payback in seconds.

Need a written answer for one location? A one-time Site Screening Report (CAD $950) delivers the same analysis as a PDF within five business days. Consultants, developers and brokers can also license the configurator and run it on their own website under their own brand.

Secure checkout by Stripe. The AI Build Configurator runs on your own website under your brand; Enterprise is quoted — compare all tiers. Annual licence. All Licence Terms and Terms of Service must be read and agreed. Terms of Service · Licence Terms

Line-item estimate, live: shell to soft costs, any state or province Put it on your website: Standard licence per domain per year

Frequently Asked Questions

How much does it cost to build a data center per megawatt?

About US$10 million to US$24 million per megawatt of IT load for the facility in 2026, depending on the build type. A hybrid mining and AI hall starts near US$6.1 million per MW, and a hyperscale AI factory with B200-class GPUs reaches about US$53 million per MW.

What is the biggest cost in building a data center?

Before GPUs, the shell and core: 57% of a 50 MW powered shell in Texas, or US$319.1M of US$563.9M. Once you buy GPUs they become the largest item, at 56% of a 100 MW AI factory in Georgia.

How long does it take to build a data center?

From about 8 months for an edge deployment to 38 months for a hyperscale AI factory, including grid connection. Grid queues alone run from 26 to 54 months depending on the state.

Which states are cheapest to build a data center in?

Arkansas and Mississippi have the lowest construction cost factor, 0.86 times the US base. Hawaii is the most expensive at 1.30 times, followed by California and New York at 1.22 times.

How can I get a cost estimate for my own site?

Run your own numbers in the free live demo of the SCR AI Build Configurator, or order a one-time Site Screening Report for CAD $950.