Power is the recurring value of the subscription. It is also the part of the model that moves for reasons nobody controls. Three provinces changed in ways that alter site selection logic, not just arithmetic.
Quebec was repriced, and it is the biggest single change in the release
Hydro-Quebec filed a dedicated rate for large data centres with the Regie de l'energie averaging 13 cents per kilowatt hour — roughly double what large-power customers pay today. It applies to facilities above 5 megawatts, is expected in force in the second half of 2026 subject to approval, and applies automatically to all new customers in the segment. Sites already connected transition to it over five years.
Alongside it, the utility proposed moving the rate for cryptographic use applied to blockchains to an average of 19.5 cents per kilowatt hour, with a three-year transition for existing customers, on the reasoning that the activity is energy intensive with limited economic return to the province.
The model moved Quebec from 5.5 cents to 13.0 cents. The practical effect is blunt: run the hybrid mining and AI profile against Quebec now and it returns negative EBITDA. That is not a modelling artefact, it is the correct signal. Under a 19.5 cent blockchain tariff the hashing side of a hybrid site does not clear its own power cost. Quebec has spent two decades as the reflexive answer to "where should we put it," and for this class of load that answer has changed. Anyone still running a Quebec hybrid thesis on 2024 numbers is working from a document that a regulator has already overtaken.
British Columbia cancelled the rate schedule the old figure was based on
Rate Schedule 1823, the stepped transmission rate, closed to all customers at the end of the fiscal 2026 billing year, and any remaining customers were moved to Rate Schedule 1830. RS 1830 is now the default transmission service rate, and from 1 April 2026 its three separate energy charges were consolidated into a single charge. The current structure is 4.914 cents per kilowatt hour on all energy, plus a demand charge of $12.178 per kVA of billing demand. Bills across the board rose roughly 3.75 percent on the same date.
For a high load factor data centre, that demand charge spreads across a lot of kilowatt hours and blends out near 6.6 cents. That is the figure the model now carries, up from 6.2 cents, and it is derived from the published tariff components rather than a rounded industry estimate.
The queue estimate moved more than the rate did. BC Hydro's process for emerging industries is a competitive allocation, not a queue — applicants compete for a finite block of capacity rather than waiting their turn. The utility received 15 applications representing close to 800 megawatts of requested load, with successful applicants notified from mid-September 2026. The model now carries 36 months for BC and flags the region as allocation-constrained, because the honest answer to "how long is the wait" in British Columbia is that there may not be a wait, there may be a refusal.
Alberta is no longer the fast lane, and v1.0 said it was
This is the province-wide change that most affects how the tool advises. Alberta spent years as the fastest interconnection path in Canada, and the model carried a 14-month queue on that basis. Provincial policy has since moved decisively.
The Alberta Electric System Operator's Phase 1 large-load allocation was capped at approximately 1,200 megawatts, and that cap was fully allocated to two projects with in-service dates in 2027 and 2028. Meanwhile the connection project list still carries roughly 19,500 megawatts of requested data load across dozens of projects. Phase 2 of the Large Load Integration programme is developing the long-term framework covering connections, planning, operations, markets and tariff, without a published completion timeline. In June 2026 the province filed a Data Centre Regulation creating a framework for loads of 75 megawatts and above, and the system operator has been building out a bring-your-own-generation pathway as the practical route for capacity beyond the interim cap.
So the queue went from 14 months to 26, and the region flag changed from fast to byog. Alberta is still a serious answer — but the answer now involves generation you bring yourself, regulatory approval for that generation, and emissions permitting, not simply a faster interconnect.
On Alberta pricing. Pool prices averaged roughly $32 per megawatt hour in the first quarter of 2026, which looks cheap. Power for delivery in 2029 was trading closer to $63 per megawatt hour. A ten-year model built on a soft spot price is a model that flatters itself. The widget's default sits above spot deliberately, and licensees modelling long-term Alberta positions should override it with the forward curve rather than the headline.
Every province, before and after
| Province | v1.0.1 rate | v1.2.0 rate | Queue change | Why |
| Quebec | $0.055 | $0.130 | 36 mo (no change) | New large data centre tariff filed; blockchain rate proposed at 19.5c |
| Nova Scotia | $0.115 | $0.120 | 24 → 26 mo | Rate drift and tighter capacity |
| Ontario | $0.098 | $0.102 | 30 → 32 mo | Rate drift; Global Adjustment still the dominant variable |
| Saskatchewan | $0.084 | $0.088 | 24 mo (no change) | Rate drift |
| New Brunswick | $0.081 | $0.084 | 20 mo (no change) | Rate drift; now the fastest realistic Canadian path at modest scale |
| Alberta | $0.078 | $0.080 | 14 → 26 mo | Phase 1 cap fully allocated; BYOG now the practical route |
| Newfoundland & Labrador | $0.068 | $0.070 | 28 mo (no change) | Rate drift; transmission and fibre still the limiters |
| British Columbia | $0.062 | $0.066 | 30 → 36 mo | RS 1823 cancelled, RS 1830 now default; competitive allocation |
| Manitoba | $0.051 | $0.055 | 26 → 28 mo | Still the cheapest industrial power in the model |
Rates are indicative blended all-in industrial figures in Canadian dollars per kilowatt hour at high load factor, for screening purposes. They are not tariff quotes. Every licensee should verify against the applicable rate schedule and their own load profile before a rate reaches a client document.