Named Projects Already Underway
| Customer | Location | Details |
| AWS | Virginia (statewide) | $35 billion investment across the state for data centers |
| Dominion Energy Virginia customer example | Richmond, VA | 900 MW data center project, with power provided in three 300 MW phases through 2033 |
Policy Update, 1 October 2026
A data centre electricity consumption tax of US$0.011 per kWh has applied since 1 July 2026 (HB 30) on grid and self-generated power, capped at US$600 million a year and scheduled through 30 June 2028; the equipment sales tax exemption was kept. The State Corporation Commission ordered on 31 July 2026 that new large loads pay directly for transmission built only to serve them, with Dominion to file within 90 days, and Prince William County ended by-right data centre development on 22 September 2026, so new sites there need a special use permit. The SCR AI Build Configurator adds the tax to modelled energy cost from version 1.4.0. At the federal level, FERC issued show-cause orders on large-load interconnection to all six RTOs and ISOs on 18 June 2026, and PJM filed a framework on 13 August 2026 under which new loads of 50 MW or more that do not bring their own capacity face curtailment ahead of other demand response from 1 June 2027.
Figures compiled from the Edison Electric Institute's "Large Load Projects and Tariffs" (September 2026) member-company summary and public regulatory filings. Confirm current tariff terms directly with Dominion Energy Virginia and the relevant state public utility commission before relying on any figure for a capital decision.
Weighing Virginia against another state or a Canadian province with a different rate and interconnection picture entirely? Run both sides of the comparison through our licensed AI data center cost configurator — it applies each jurisdiction's actual power rate, tax treatment and large-load tariff rules to the same seven build configurations.
Dominion’s GS-5 tariff is one of the most closely watched large-load rate designs in the country; our own crypto data center in BC runs under a very different hydroelectric rate structure for comparison.