Utility Tariff Analysis · Updated September 2026

AEP Ohio's 25 MW / 85% Minimum-Take Tariff: What It Means for AI Data Center Siting in Ohio

New data centers larger than 25 MW must pay for at least 85 percent of the energy they expect to need each month, even if they use less, to cover the cost of infrastructure needed to bring electricity to the facility.

Ohio at a glance: industrial power about 8.3¢/kWh (EIA-based, indexed to April 2026) · grid queue about 42 months · data center equipment tax exemption: paused. Indicative figures from the SCR AI Build Configurator v1.4.0.

Ohio AI data center power map: AEP Ohio's 25 MW / 85% Minimum-Take Tariff large-load tariff

AEP Ohio's 25 MW / 85% Minimum-Take Tariff

OH

AEP Ohio

24-0508-EL-ATA

Regulatory docket / filing reference

New data centers larger than 25 MW

Who the tariff applies to

New data centers larger than 25 MW must pay for at least 85 percent of the energy they expect to need each month, even if they use less, to cover the cost of infrastructure needed to bring electricity to the facility.

Also active in Ohio: FirstEnergy's Ohio Edison, Cleveland Electric Illuminating and Toledo Edison jointly filed a parallel Data Center Tariff (DCT) in June 2026 (docket 26-0697-EL-ATA), and Duke Energy Ohio has proposed its own Data Center Tariff, Rate DC (docket 26-0755-EL-ATA).

Ohio at a glance: large-load tariff threshold, docket and who it applies to

Named Projects Already Underway

CustomerLocationDetails
AWSNew Albany, OHpart of a $7.8 billion AWS investment in Central Ohio and $23 billion statewide by 2030; AEP Ohio contracted two large customers for 100 MW of onsite fuel-cell generation to let data centers begin operating while the grid expands
Undisclosed hyperscale campusPiketon, OH$33 billion project proposing up to 10 GW of generation, with partner SB Energy paying $4.2 billion for new transmission to avoid raising rates for existing customers

Figures compiled from the Edison Electric Institute's "Large Load Projects and Tariffs" (September 2026) member-company summary and public regulatory filings. Confirm current tariff terms directly with AEP Ohio and the relevant state public utility commission before relying on any figure for a capital decision.

Weighing Ohio against another state or a Canadian province with a different rate and interconnection picture entirely? Run both sides of the comparison through our licensed AI data center cost configurator — it applies each jurisdiction's actual power rate, tax treatment and large-load tariff rules to the same seven build configurations.

AEP Ohio’s minimum-take requirement changes the math on committed capacity; our crypto data center in BC runs under a different commitment structure entirely, worth reviewing for contrast.

Named data center projects underway in Ohio Named Projects Already Underway: AEP Ohio's 25 MW / 85% Minimum-Take Tariff: What It Means for AI Data Center Siting in Ohio

Model This State on Your Own Site

Every figure above comes from the same power-cost and tariff dataset behind the SCR AI Build Configurator — a licensed, embeddable widget that models seven data center build configurations against all nine Canadian provinces and all 50 US states plus DC, returning capital expenditure by line item, energy cost, revenue by commercial structure, EBITDA and payback.

LicencePrice (CAD)Who it suits
Standard$4,000 / domain / yearAdvisors who need three lease-model configurations and a clipboard summary
Pro$10,000 / domain / yearConsultants who send CSV deliverables to clients and want all seven configurations
EnterpriseFrom $25,000 / year, up to 3 domainsDevelopers and EPC firms who want the model on their own cost basis with attribution removed

Not ready for an annual licence? A one-time Site Screening Report ($950, one site) runs the same model for a single build without embedding anything.

Model a Ohio data center build in the SCR AI Build Configurator: CapEx, power cost, EBITDA and payback Model This State on Your Own Site: AEP Ohio's 25 MW / 85% Minimum-Take Tariff: What It Means for AI Data Center Siting in Ohio

Compare Ohio With Nearby States

Large-load rules change sharply at state lines. See how the neighbouring utilities handle data center and high-density loads before you shortlist a site.

Frequently Asked Questions

What is AEP Ohio's 25 MW / 85% Minimum-Take Tariff?

New data centers larger than 25 MW must pay for at least 85 percent of the energy they expect to need each month, even if they use less, to cover the cost of infrastructure needed to bring electricity to the facility.

Why did AEP Ohio introduce this large-load structure?

To ensure the cost of new generation, transmission and distribution infrastructure built to serve very large customers, chiefly hyperscale data centers, is paid for by those customers rather than spread across the general rate base of residential and small commercial ratepayers.

What else should data center developers know about Ohio?

FirstEnergy's Ohio Edison, Cleveland Electric Illuminating and Toledo Edison jointly filed a parallel Data Center Tariff (DCT) in June 2026 (docket 26-0697-EL-ATA), and Duke Energy Ohio has proposed its own Data Center Tariff, Rate DC (docket 26-0755-EL-ATA).

Does this tariff replace Ohio's standard commercial and industrial rates?

No. AEP Ohio's 25 MW / 85% Minimum-Take Tariff sits above AEP Ohio's standard commercial and industrial rate schedules and applies specifically to customers that meet or exceed the large-load threshold described above. Smaller commercial and industrial loads continue to be billed under existing rate schedules.

How can I model a Ohio data center build against this tariff and other states?

The SCR AI Build Configurator applies Ohio's power cost, tax treatment and large-load tariff rules alongside all other US states and Canadian provinces, so a Ohio scenario can be compared line-by-line against any alternative site.